Add to homescreen

If you want to add this app to home screen tap and then ‘Add to Home Screen’.

Scaffold installation near energised power line

What happened - icon

What happened?

To assist in making a new electrical connection, a scaffold crew was asked to erect scaffolding near uninsulated, energised, power pole components and overhead power lines.

The scaffold crew was unaware that the system was energised.

While the crew erected the scaffold, a contractor supervisor recognised energised electrical equipment and stopped the work.

A worker stood on a scaffold approximately 2 metres off the ground, building the scaffolding next to power pole components with overhead power lines.
What happened - icon

Why did it happen?

The work scope identified the need for energy isolation prior to scaffold work, however, failures in the permit to work and hot work permitting processes meant the work scope was inadequate and relevant work tasks and associated hazards were not considered.

It was not recognised that a unit work permit needed to be obtained for the scaffold task.

Contractor toolbox meeting occurred at the drill site and energy isolation was discussed, however, the scaffold crew did not attend.

Lack of effective pre‐job communication and walk down allowed the scaffold crew to proceed without effective energy isolation in place.

The scaffolding in front of the uninsulated, energized power pole components and overhead power lines.
What happened - icon

What did they learn?

Know and understand:

  • How the permit to work (PtW) procedure applies to your scope of work and when permits are required.
  • Standard procedure for energy isolation and how it applies to your job tasks.

Review and improve PtW process. If necessary, include practices that focus on electrical work and control of work (field execution, governance, verification).

Always incorporate a pre-job meeting and walkdown with all involved employees to identify critical and high hazard activities.

In safety meetings, reaffirm the need to reassess changing conditions and reaffirm people’s authority to stop work.

When multiple permits are required, consider using a simultaneous operations coordinator/project operator.

If necessary, conduct contractor training/refresher training on energy isolation, PtW roles and responsibilities, hazard recognition and scaffold electrical clearance distances.

What happened - icon

Ask yourself or your crew

How can something like this happen here?

How do we make sure the right people (or everyone) attends toolbox meetings?

What could have happened if the supervisor did not recognise that the system is energised and initiate stop work procedure?

Have you ever been in a similar position as part of a contracted crew? Why was that?

Do you fully understand when a PtW is required?  How can we improve the way we use the PtW system?

  • What happened?

    To assist in making a new electrical connection, a scaffold crew was asked to erect scaffolding near uninsulated, energised, power pole components and overhead power lines.

    The scaffold crew was unaware that the system was energised.

    While the crew erected the scaffold, a contractor supervisor recognised energised electrical equipment and stopped the work.

    A worker stood on a scaffold approximately 2 metres off the ground, building the scaffolding next to power pole components with overhead power lines.
  • Why did it happen?

    The work scope identified the need for energy isolation prior to scaffold work, however, failures in the permit to work and hot work permitting processes meant the work scope was inadequate and relevant work tasks and associated hazards were not considered.

    It was not recognised that a unit work permit needed to be obtained for the scaffold task.

    Contractor toolbox meeting occurred at the drill site and energy isolation was discussed, however, the scaffold crew did not attend.

    Lack of effective pre‐job communication and walk down allowed the scaffold crew to proceed without effective energy isolation in place.

    The scaffolding in front of the uninsulated, energized power pole components and overhead power lines.
  • What did they learn?

    Know and understand:

    • How the permit to work (PtW) procedure applies to your scope of work and when permits are required.
    • Standard procedure for energy isolation and how it applies to your job tasks.

    Review and improve PtW process. If necessary, include practices that focus on electrical work and control of work (field execution, governance, verification).

    Always incorporate a pre-job meeting and walkdown with all involved employees to identify critical and high hazard activities.

    In safety meetings, reaffirm the need to reassess changing conditions and reaffirm people’s authority to stop work.

    When multiple permits are required, consider using a simultaneous operations coordinator/project operator.

    If necessary, conduct contractor training/refresher training on energy isolation, PtW roles and responsibilities, hazard recognition and scaffold electrical clearance distances.

    What learn - icon
  • Ask yourself or your crew

    How can something like this happen here?

    How do we make sure the right people (or everyone) attends toolbox meetings?

    What could have happened if the supervisor did not recognise that the system is energised and initiate stop work procedure?

    Have you ever been in a similar position as part of a contracted crew? Why was that?

    Do you fully understand when a PtW is required?  How can we improve the way we use the PtW system?

    Ask your crew - icon
Published on 13/11/19 3907 Views

A scaffold crew was directed to erect scaffolding within 15 feet/5 metres of an energised and uninsulated system. Work started, unaware that the system was powered. A supervisor recognised the energised electrical equipment and stopped work immediately.