Add to homescreen

If you want to add this app to home screen tap and then ‘Add to Home Screen’.

Two workers lost their lives when entering a pipe after welding operations

What happened - icon

What happened?

Two welders were repairing an external weld on a vertically orientated 34" pipe spool.

After finishing, the first welder used a ladder to enter the pipe to inspect the repair.

The welder collapsed after entering the pipe due to entering an oxygen-depleted atmosphere.

The second welder entered the pipe to rescue the first, but also collapsed.

The safety adviser was alerted, and the site emergency response team (ERT) were called.

Workers positioned a fan blowing fresh air into the pipe.

Against the advice from colleagues, a third worker entered the pipe and tied a rope around one of the welders, hoisting him out.

Site ERT arrived – one of the ERT team entered the pipe and retrieved the second welder.

Both welders lost their lives.

What happened - icon

Why did it happen?

Entry into the pipe spool was unplanned and unauthorised. The repair was supposed to be carried out externally, so the workers did not have confined space permit controls and had not undertaken risk management processes.

A poor-quality non-proprietary argon purge dam was used.

After removing the argon weld purge dam, no ventilation of the pipe spool occurred.

The pipe spool was not capped.

Neither argon or confined space advisory signs were on the pipe or in the purge area.

Onboarding induction contained limited information on inert gas safety.

What happened - icon

What did they learn?

Ensure workers understand that entry into pipe spools should only be a last resort and under a confined space permit.

Ensure lockable covers are installed on open pipe ends greater than 18”.

Develop and implement the following training programmes:

  • Installation, utilisation, and removal of purge dams.
  • Inert gas awareness.
  • Line blowing.

Improve safety signage on site.

Investigate other options to negate the need for argon purge welding.

Ensure identified defects are discussed with the welding engineer to determine correct diagnosis and associated repairs.

Ensure workers have the correct tools for their tasks.

Undertake a review of emergency response arrangements.

What happened - icon

Ask yourself or your crew

Do we expect to need to enter a confined space to complete today’s activity?

Do you have all the correct permits in place for your work?

What do we have in place to prevent or deter people from entering confined spaces? (Think signage, equipment, procedures)

If confined space entry is required:

  • Is there a safer way to do the job that doesn’t require confined space entry?
  • What precautions have we put in place to ensure it is safe? What more can we do?
  • What is our emergency response procedure?
  • What happened?

    Two welders were repairing an external weld on a vertically orientated 34" pipe spool.

    After finishing, the first welder used a ladder to enter the pipe to inspect the repair.

    The welder collapsed after entering the pipe due to entering an oxygen-depleted atmosphere.

    The second welder entered the pipe to rescue the first, but also collapsed.

    The safety adviser was alerted, and the site emergency response team (ERT) were called.

    Workers positioned a fan blowing fresh air into the pipe.

    Against the advice from colleagues, a third worker entered the pipe and tied a rope around one of the welders, hoisting him out.

    Site ERT arrived – one of the ERT team entered the pipe and retrieved the second welder.

    Both welders lost their lives.

    What happened - icon
  • Why did it happen?

    Entry into the pipe spool was unplanned and unauthorised. The repair was supposed to be carried out externally, so the workers did not have confined space permit controls and had not undertaken risk management processes.

    A poor-quality non-proprietary argon purge dam was used.

    After removing the argon weld purge dam, no ventilation of the pipe spool occurred.

    The pipe spool was not capped.

    Neither argon or confined space advisory signs were on the pipe or in the purge area.

    Onboarding induction contained limited information on inert gas safety.

    Why did it happen - icon
  • What did they learn?

    Ensure workers understand that entry into pipe spools should only be a last resort and under a confined space permit.

    Ensure lockable covers are installed on open pipe ends greater than 18”.

    Develop and implement the following training programmes:

    • Installation, utilisation, and removal of purge dams.
    • Inert gas awareness.
    • Line blowing.

    Improve safety signage on site.

    Investigate other options to negate the need for argon purge welding.

    Ensure identified defects are discussed with the welding engineer to determine correct diagnosis and associated repairs.

    Ensure workers have the correct tools for their tasks.

    Undertake a review of emergency response arrangements.

    What learn - icon
  • Ask yourself or your crew

    Do we expect to need to enter a confined space to complete today’s activity?

    Do you have all the correct permits in place for your work?

    What do we have in place to prevent or deter people from entering confined spaces? (Think signage, equipment, procedures)

    If confined space entry is required:

    • Is there a safer way to do the job that doesn’t require confined space entry?
    • What precautions have we put in place to ensure it is safe? What more can we do?
    • What is our emergency response procedure?
    Ask your crew - icon
Published on 04/08/21 2987 Views

Two welders were repairing an external weld on a pipe spool. One worker entered the pipe to check the weld and collapsed. The second worker tried to recover his colleague and also collapsed.