Add to homescreen

If you want to add this app to home screen tap and then ‘Add to Home Screen’.

Wind farm outage during load rejection test

What happened - icon

What happened?

During commissioning activities at a wind turbine generator (WTG) site, a load rejection test was conducted while all personnel were returning to port.

The test involved remotely opening and closing a circuit breaker, initially producing approximately 2 MW according to the procedure.

Immediately after closing the circuit breaker, the entire wind farm and the shore circuit breaker tripped, and smoke detectors in a WTG foundation were activated.

Subsequent inspection revealed a burst chimney above the switchgear compartment and an exploded surge arrester on phase L3.

Burst chimney above the switchgear compartment
What happened - icon

Why did it happen?

Potential gradual degradation of the phase L3 surge arrester due to prior overvoltage events and a possible overload from a fault in the associated circuit breaker.

Insufficient monitoring and data analysis from SCADA (supervisory control and data acquisition) and previous tests, which could have provided early warning of the issue.

Unprecedented nature of the event (the first of its kind on site) contributed to the lack of prior detection or preventive measures.

What happened - icon

What did they learn?

An investigation was conducted to identify the root cause, and replace faulty switchgear as required, followed by commissioning and validation of safe operation.

Defective equipment was returned to the supplier for final root cause analysis.

Implemented a strict risk assessment and permit-to-work procedures for all electrical tests and remote switching operations, ensuring offshore personnel are in safe locations.

Teams must maintain appropriate fire detection and suppression systems near high-risk electrical equipment, and utilise SCADA for early detection and improved remote monitoring.

Enhance data availability, remote control capabilities, and ensure personnel and manufacturer teams have proper training and electrical accreditation for safe offshore intervention.

What happened - icon

Ask yourself or your crew

How can we better use SCADA and data to detect issues early?

What extra risk assessments or permits should we apply for electrical tests?

How can we ensure offshore personnel stay safe during high-risk operations?

Are fire detection and suppression systems sufficient near critical equipment?

How can we improve training and readiness for safe offshore electrical interventions?

  • What happened?

    During commissioning activities at a wind turbine generator (WTG) site, a load rejection test was conducted while all personnel were returning to port.

    The test involved remotely opening and closing a circuit breaker, initially producing approximately 2 MW according to the procedure.

    Immediately after closing the circuit breaker, the entire wind farm and the shore circuit breaker tripped, and smoke detectors in a WTG foundation were activated.

    Subsequent inspection revealed a burst chimney above the switchgear compartment and an exploded surge arrester on phase L3.

    Burst chimney above the switchgear compartment
  • Why did it happen?

    Potential gradual degradation of the phase L3 surge arrester due to prior overvoltage events and a possible overload from a fault in the associated circuit breaker.

    Insufficient monitoring and data analysis from SCADA (supervisory control and data acquisition) and previous tests, which could have provided early warning of the issue.

    Unprecedented nature of the event (the first of its kind on site) contributed to the lack of prior detection or preventive measures.

    Why did it happen - icon
  • What did they learn?

    An investigation was conducted to identify the root cause, and replace faulty switchgear as required, followed by commissioning and validation of safe operation.

    Defective equipment was returned to the supplier for final root cause analysis.

    Implemented a strict risk assessment and permit-to-work procedures for all electrical tests and remote switching operations, ensuring offshore personnel are in safe locations.

    Teams must maintain appropriate fire detection and suppression systems near high-risk electrical equipment, and utilise SCADA for early detection and improved remote monitoring.

    Enhance data availability, remote control capabilities, and ensure personnel and manufacturer teams have proper training and electrical accreditation for safe offshore intervention.

    What learn - icon
  • Ask yourself or your crew

    How can we better use SCADA and data to detect issues early?

    What extra risk assessments or permits should we apply for electrical tests?

    How can we ensure offshore personnel stay safe during high-risk operations?

    Are fire detection and suppression systems sufficient near critical equipment?

    How can we improve training and readiness for safe offshore electrical interventions?

    Ask your crew - icon
Published on 31/07/26 51 Views

Electrical equipment failed during a wind farm load rejection test, causing smoke alarm activation and breaker trips.