Add to homescreen

If you want to add this app to home screen tap and then ‘Add to Home Screen’.

Transition piece destabilises and falls

What happened - icon

What happened?

A transition piece (TP) was prepared for load out.

Shortly after the start of the lift, the internal system detected a difference in the loads between the three hooks, and it was automatically stopped.

Hook 1 was not able to hold the load which meant it descended, while hook 2 and 3 stayed at the same height.

This caused the transition piece to fall into a vertical unstable position.

The spreader then came down and pulled the transition piece into a horizontal position on the cellar deck platform.

Transition piece fallen on the cellar deck platform
What happened - icon

Why did it happen?

There was a mechanical failure in hook 1, which allowed the load to descend.

Although the maintenance of the overhead crane was performed by an experienced external company and witnessed by third party inspection:

  • no full load test was performed on the system
  • there were no predefined points for inspection after or during maintenance
  • the technician did not have sufficient technical knowledge

The risk of the spreader beam falling was not considered.

Spreader beam
What happened - icon

What did they learn?

An extra set of safety breaks should be fitted on the rotors (working as a parallel safety option).

Full load tests should be undertaken after adaptation or replacement of critical components.

Ensure that the basis of the support system is large enough, so if there is movement in the TP, the support does not fall.

Maintenance procedures should be reviewed regularly to ensure that they are fit for purpose and suitable for any new or modified task carried out by the crane.

What happened - icon

Ask yourself or your crew

What controls do we have in place to prevent this from happening on our site?  How do we know this will be effective?

Why should we have predefined inspection points after maintenance activities?

What other hazards should you look out for during lifting operations on transition pieces?

  • What happened?

    A transition piece (TP) was prepared for load out.

    Shortly after the start of the lift, the internal system detected a difference in the loads between the three hooks, and it was automatically stopped.

    Hook 1 was not able to hold the load which meant it descended, while hook 2 and 3 stayed at the same height.

    This caused the transition piece to fall into a vertical unstable position.

    The spreader then came down and pulled the transition piece into a horizontal position on the cellar deck platform.

    Transition piece fallen on the cellar deck platform
  • Why did it happen?

    There was a mechanical failure in hook 1, which allowed the load to descend.

    Although the maintenance of the overhead crane was performed by an experienced external company and witnessed by third party inspection:

    • no full load test was performed on the system
    • there were no predefined points for inspection after or during maintenance
    • the technician did not have sufficient technical knowledge

    The risk of the spreader beam falling was not considered.

    Spreader beam
  • What did they learn?

    An extra set of safety breaks should be fitted on the rotors (working as a parallel safety option).

    Full load tests should be undertaken after adaptation or replacement of critical components.

    Ensure that the basis of the support system is large enough, so if there is movement in the TP, the support does not fall.

    Maintenance procedures should be reviewed regularly to ensure that they are fit for purpose and suitable for any new or modified task carried out by the crane.

    What learn - icon
  • Ask yourself or your crew

    What controls do we have in place to prevent this from happening on our site?  How do we know this will be effective?

    Why should we have predefined inspection points after maintenance activities?

    What other hazards should you look out for during lifting operations on transition pieces?

    Ask your crew - icon
Published on 18/03/22 2605 Views

A transition piece (TP) was prepared for load out. Shortly after the start of the lift, the internal system detected a difference in the loads between the three hooks. Following a sequence of events, the transition piece to fell on the cellar deck platform.